Mamre provides efficient commercial HVAC installations for a wide variety of businesses. We’ve worked with healthcare, retail, historical buildings, hospitality, facilities. Our dedicated team produces high quality workmanship and incredible attention to detail on every project. We place an emphasis on customer service and offer energy- and cost-saving solutions whenever possible.
Quite simply our team members are committed to ensuring that every commercial HVAC system we touch has the proper fit, features, and installation. If you’re ready to begin a new project, don’t hesitate to reach out to us today.
Case Study 1
St. Ann’s School
Overview
Client: Yorke Construction
Completed: June 2018
Contract Bid: $3.4mm
Description
St. Ann’s School is a Brooklyn-based independent school and historical landmark that required a substantial retrofit of the building’s mechanical system.
To modernize the building’s HVAC system, Mamre installed a 190-ton chiller, a 60-ton energy recovery air handler, and completed a steam boiler retrofit.
Mechanical installations within historical buildings are typically complex because they require working within strict architectural constraints. Mamre’s approach to problem-solving through the installation phase ensured that the building was upgraded to a 21st-century mechanical system while respecting the limitations provided by the historical landmark, and ensuring the project was completed in time for the start of the school year.
Equipment
190 ton Trane chiller
60 ton Energy Recovery Air Handler
Case Study 2
5th Avenue Synagogue
Overview
Client: Shawmut
Completed: Phase I completed in June 2021, Phase ongoing through 2022
Contract Bid: $2.4 mm
Description
The 5th Avenue Synagogue building is a historical landmark at the heart of midtown Manhattan dating back to the 1950s.
For this project, Mamre collaborated with MD Mechanical to deliver a brand new mechanical system for the building while maintaining the architectural integrity of the Synagogue, an important client requirement.
Throughout the installation phase, Mamre provided the client with innovative alternative installation solutions to avert challenges that arose during the construction phase that could have resulted in a deviation from the building’s architectural intent.
Phase I of the project was delivered on time while ensuring the building remained operational. Phase II is on-going through 2022.
Equipment
Aermec 30 ton outside air unit
25 Aermec fan coil system
Alerton BMS system
“On behalf of our team, I want to thank you for your incredible work on the Newlab project in the Brooklyn Navy Yard. You are, by far, the best mechanical contractor we have worked with, and are excited to work with you on as many future projects as possible.”
James Neu
Partner, DBI Projects
“I have had the pleasure of working with Mamre Heating & Cooling on a number of projects. Mamre has been able to quickly adapt to any changed to accomplish the project goals. I am happy to recommend Mamre and look forward to working with them again.”
MD Aminul Islam, PE, CEM, EBPC
President & CEO, NY Building Systems Consultants